Tank refurbishment 4 min read

What is WRAS approved tank coating?

If you reline a cold water storage tank, the coating you choose sits in direct contact with water that people drink, wash in and shower in. Approval for potable water contact is not a nice extra — it is the baseline.

What approval means

WRAS approval indicates that a product has been tested against the requirements of the Water Supply (Water Fittings) Regulations and is accepted as suitable for contact with wholesome water, so it does not impart taste, odour, colour or harmful substances into the supply. In England and Wales, products used in contact with drinking water also fall under regulation 31, and the relevant approval reference should be available from the manufacturer.

In practice, always ask for the product name and its approval reference, and check that it is current and appropriate for the application — a coating approved for occasional contact is not the same as one approved for continuous immersion in a potable water tank.

Approval does not guarantee a good job

An approved coating applied badly is still a bad tank. Surface preparation determines performance: all loose coating, corrosion, scale and contamination must be removed, pits and seams repaired, and the surface prepared to the standard the product requires. Application at the specified film thickness, in the specified number of coats, with the right cure time and inspection of the finished surface, is what produces a lining that lasts.

  • Documented surface preparation standard
  • Product name and approval reference on the completion report
  • Wet and dry film thickness measurements recorded
  • Cure verified before disinfection and return to service
  • Post-work cleaning, disinfection and sampling

What happens after coating

Once cured, the tank is cleaned, disinfected to HSG274 Part 2, flushed and sampled before it returns to service — the coating does not remove the need for that step, and the first sample after relining is your proof that the tank is now fit to supply.

This article is general guidance, not a site-specific risk assessment. Control measures for your building should follow your written scheme of control and the Approved Code of Practice L8 with HSG274.