Sampling 6 min read

What is involved in a Legionella sampling programme?

A sampling programme is more than a calendar of visits. Done properly it is a designed set of sample points and parameters that tells you whether the controls described in your risk assessment are working.

Start from the risk assessment and the schematic

Sample points should reflect the actual system: incoming cold supply, each storage tank outlet, calorifier flow and return, sentinel outlets near and far, the furthest outlet on each range, and any outlet serving a high-risk population. Without an up-to-date schematic you cannot know whether the points you are sampling are representative.

How many points and how often

A typical commercial building might have between six and twenty routine points depending on size and complexity, with additional points for cooling systems, spa systems or high-risk areas. Frequency usually starts at six-monthly for a well-controlled domestic system and increases where results have been unsatisfactory, where the building has little-used outlets, or where the population is vulnerable.

Routine frequency should be stated in the written scheme of control. Sampling more often than the scheme says is not a problem; sampling less often is, and is the kind of gap an inspector will look for in your records.

Procedure matters as much as the laboratory

Samples must be taken correctly: the right bottle with the correct neutralising agent, the outlet flushed or not flushed according to the sample type, temperature and residual chlorine measured and recorded at the point of sampling, and the sample delivered to the laboratory within the required time. Poor sampling produces results that are either falsely reassuring or falsely alarming, and either way they are a waste of the money you spent on analysis.

Using the results

A useful report shows each sample point, the result, the interpretation against HSG274 thresholds, and the trend against the previous two visits. It should end with a recommendation, not just data. Over a year, the pattern of results — not any single result — is what demonstrates that the system is under control.